Project and phase budgeting

How budgeting works for projects and phases

Product line

Standard

|

Expert

Operating mode

CLOUD ABO

|

ON-PREMISES

Modules

Services & CRM

Budget & Phases

Purchases

Resource Planning

Business Intelligence

Created: 13.11.2006
Updated: 17.06.2022 | Added detailed list to the planned values.

Budget values can be defined for projects and phases. These are used to compare planned and actual values. In this way, evaluations such as 'phases with budget overrun’ can be made. On fixed-price phases, the fixed amount is determined with the budget values.

The following values can be planned:

Services
Value Description Attribute
Hours

This is about planning how much time your employees will actually enter for this project.

This allows you to compare how much time you were able to charge and how much was actually spent.

planMinutenInt
Fee

Planned amount that you should actually be able to charge to your customers (charged or “external” fee). It is the amount that the end customer sees on the invoice, i.e. billable time * ext. hourly rate.

Normally, the external fee for a service is the product of hours and hourly rate. However, before charging, this amount can be adjusted manually to charge a different amount.

planWertExt
Internal fee

Internal fee does not refer to the costs. It is the amount that one would theoretically or could bill to the end customer. This corresponds to the working time * ext. hourly rate. In the case of a flat rate, for example, this can be more or less than the billable amount. With the internal fee, an additional controlling figure is available.

At project phases, internal fees can also be used for Poc calculations, in which the planned total costs are estimated periodically and entered as “internal fees”.   Tracking planned values on phases the raw data are then available for a PoC calculation.

Unlike external fees (see above), the internal, recorded value is never adjusted at the time of charging.

planWertInt
Cost

This value is used to plan the internal costs incurred for this project – the so-called standard costs.

This value is important for internal cost accounting and can be evaluated via the Business Intelligence module.

What is included in these costs depends on what contribution margin you want to see in the Business Intelligence module. In most cases, only the pure salary and direct ancillary salary costs are taken. The same value is taken if you want to post via internal performance accounting (ILV), since costs such as rent, IT, etc. are transferred from cost accounting to KST.

planKostenLeistung
Expenses
Value Description Attribute
Amount Planned amount of expenses that you charge to your customers. planSpesenWert
Cost Planned amount of expenses that you enter internally. planKostenSpesen
Outlays
Value Description Attribute
Amount Planned amount of outlays that you charge to your customers. planAuslagenWert
Cost Planned amount of outlays that you have to enter internally or pay to suppliers. planKostenAuslagen

In System settings > Project tab, you can define whether or not the Show totals checkbox is activated by default.

play-button

Presentation

  • Green: The values were budgeted on the project/phase itself.
  • Black: The values have been budgeted on a subphase or phase allocation, where this assignment has the following hierarchy:
    • For projects: The values were budgeted at one phase.
    • in the case of phases:
      1. If subphases are present, the budget values are taken from them, if values are set there.
      2. If user assignments exist, these budget values are taken (even if they are 0).
      3. If there are no user assignments, the budgets are used on the activity assignments for the services budget, the budgets are used on the expense type assignments for the expense budget, and the budgets are used on the expense type assignment for the expense budget.

    When calculating budget totals based on phases, phases with the status offer and rejected are not considered.

Tracking planned values

For phases, changes to budget values can be tracked. See Tracking planned values on phases.